ADU Project · Lakewood, CA

Every invoice, estimate, and receipt in one place.

A running log of the ADU build: what Team Champion has billed directly, what the contracted estimates cover, what's been paid, and what's still outstanding — grouped into City Fees, Construction, Finishings, and Main House Improvements.

Overview

Spend by category

Total contracted/billed amount, grouped into the four project buckets

Paid vs. outstanding

How much of the total project cost has actually been paid so far

Project Status

Status as of Oct 29, 2026. Final inspection has passed; what remains is punch list work.

  • Final inspection passed on Sep 25, 2026, and the City finalized the project. All Team Champion invoices are marked paid as of Oct 27.
  • Solar PV: the ADU was confirmed as not requiring solar (phone confirmation reported Sep 15). The exemption paperwork was still being completed at that time.
  • Open punch list (reported to Team Champion Oct 2 to Oct 15, completion not yet confirmed): dishwasher circuit trips and the dishwasher is not attached to the cabinet; missing baseboard behind the front door; loose outdoor dryer vent; gutter leak over the breezeway; gas dryer reports the gas is not supplied smoothly (suspected gas line).
  • Main house back doors: both exterior doors are about 3 inches too short for their openings. The plan (Sep 21) is to reframe both openings with new headers. No cost has been quoted yet.
  • Pending quote: gutters for the house and garage. Garage door work was deferred to next year's project.

Project Details

Every invoice, estimate, material purchase, payment, and photo on record

Key dates from first contact to present — contract milestones, inspections, payments, and delays. Meeting requests and routine back-and-forth are left out; this tracks forward progress only.

A curated set of photos from the build, organized by phase. Videos aren't included yet.

Billed directly to the owner by Team Champion or another vendor — not part of the estimate/installment flow

Invoice #VendorDateDescriptionCategoryAmountPaidBalance
IN-26023 (Terreno Land Surveying, $2,200) was paid via Zelle directly, so there's no Houzz-style PDF receipt for it — marked paid based on owner confirmation.
IN-10490 passes through a So Cal Industries portable restroom rental and kitchen countertop materials. Team Champion did not itemize the amounts, so the full $2,617.65 is placed in Construction (ADU).

Contracted construction scopes, paid down in installments per each estimate's own terms

Estimate #DateDescriptionCategoryStatusAmountPaidBalance
ES-10457 (Main Water Supply Line, $5,200) was originally quoted as an estimate but was billed and paid as invoice IN-10396, a one-off exception to the normal process. It is listed here for reference and excluded from the totals so the $5,200 is counted once.
Estimate-to-invoice conversions. Team Champion converted ES-10290, ES-10437, ES-10468, ES-10511, ES-10546 and CO-10047 into final invoices IN-10488, IN-10478, IN-10486, IN-10487, IN-10485 and IN-10489. Those invoices consolidate the estimate payments already made, so they appear here once and not again on the Invoices tab. ES-10290 reflects a $1,997.92 credit for tile returned to Floor & Decor.
ES-10468 (New Foundation, $23,700) was paid by bank wire. Texts show David asked for the first payment on Feb 16, 2026 and the owner replied he would wire it that day. No Houzz receipt exists, so the Feb 16 date on the Payments tab is an estimate and the $20 wire fee follows the flat-fee convention.

Direct purchases (Lowe's, Home Depot, etc.) that don't run through a Team Champion invoice or estimate

DateVendorItem(s)CategoryAmountPaidOrder #

Lowe's order history gives order-level totals only, not a per-item price breakdown — so each order is one row rather than one row per appliance/fixture.

Every Houzz Pro payment receipt, chronological. Credit card payments carry a 3% transaction fee + 0.6% platform fee; wire transfers carry a flat $20 fee.

DateApplied toTypeMethodAmount paidFeesTotal charged

Two paid items don't appear here because they weren't routed through Houzz: IN-26023 (Zelle, no receipt) and the BUSD Developer Fee (cashier's check, receipt filed separately). The Feb 16 foundation wire ($23,700) is listed with an estimated date because no receipt exists.

The Aug 10 wire ($21,800, split across ES-10511 and ES-10546) is documented by Team Champion's email confirmation rather than a Houzz receipt. The Oct 9 wire covered four invoices in one transfer. Each wire carries one $20 fee following the convention above; the card fee on IN-10491 comes from its Houzz receipt ($21.00 transaction fee + $4.20 platform fee).